Current Projects | Executed Projects
Year of Award
Type
Project
Client
Engineer/ Architect
Original Value $
Percentage of Execution as of 31/10/2009
Start Date (Actual/ Projected)
Complete Date (Actual/ Projected)
2008
Eclairage Signalisation
Zahrani-Qana Incidental
C.D.R.
Conser
3,760,728
64.76%
14/08/2008
14/08/2011
Highway
Zahrani-Qana Phase 4
7,554,519
60.72%
13/11/2008
13/05/2011
Upgrading of Hazmieh - Saoufar International Road Section 1 (A-B)
Khatib & Alami
37,284,106
3.74%
02/03/2009
02/09/2011
2007
Pan Arab Highway Mdairej – Chtaura – Taanayel Section
Team Intl. - Saudconsult
157,735,000
1.78%
29/04/2009
29/04/2014
Infrastructure
Grade Separation At Tayyouneh Roundabout
11,779,359
37.86%
01/10/2007
15/04/2011
Beirut City Services Upgrading Project Phase 2, Package III & IV, Contract 2, Stage 1
Dar Al Handasah
21,794,086
(Projected)
72.51%
02/05/2007*
02/05/2010
Beirut City Services Upgrading Project Phase 2, Package III & IV, Contract 2, Stage 2
10,903,996
0%
15/11/2009
14/11/2010
2005
West Bekaa Wastewater Project
Dar Al-Handasah
32,795,956
92.23%
10/11/2005
30/09/2010
TOTAL
283,607,760