Current Projects | Executed Projects

 

Year of Award

Type

Project

Client

Engineer/ Architect

Original Value $

Percentage of Execution as of 31/10/2009

Start  Date (Actual/ Projected)

Complete Date (Actual/ Projected)

 2008

Eclairage Signalisation

Zahrani-Qana Incidental

C.D.R.

Conser

3,760,728

64.76%

14/08/2008

14/08/2011

 2008

Highway

Zahrani-Qana Phase 4

C.D.R.

Conser

7,554,519

60.72%

 13/11/2008

 13/05/2011

 2008

Highway

Upgrading of Hazmieh - Saoufar International Road Section 1 (A-B)

C.D.R.

Khatib & Alami

37,284,106

3.74%

 02/03/2009

 02/09/2011

 2007

Highway

Pan Arab Highway Mdairej – Chtaura – Taanayel Section

C.D.R.

Team Intl. - Saudconsult

157,735,000

1.78%

29/04/2009

29/04/2014

 2007

Infrastructure

Grade Separation At Tayyouneh Roundabout

C.D.R.

Team Intl. - Saudconsult

11,779,359

37.86%

01/10/2007

15/04/2011

 2007

Infrastructure

Beirut City Services Upgrading Project Phase 2, Package III & IV, Contract 2, Stage 1

C.D.R.

Dar Al Handasah

21,794,086

 

(Projected)

72.51%

02/05/2007*

02/05/2010

 2007

Infrastructure

Beirut City Services Upgrading Project Phase 2, Package III & IV, Contract 2, Stage 2

PictureFolder.bmp

C.D.R.

Dar Al Handasah

10,903,996

 

(Projected)

 

0%

15/11/2009

14/11/2010

2005

Infrastructure

West Bekaa Wastewater Project

C.D.R.

Dar Al-Handasah

 

32,795,956

 

(Projected)

92.23%

10/11/2005

30/09/2010

 

 

 

 

TOTAL

283,607,760