Beirut City Services Upgrading Project Phase 2, Package III & IV, Contract 2, Stage 1

 

 

DESCRIPTION OF WORK AND SITE

General Description

The Works include the construction of a tunnel and the new construction and the rehabilitation of Infrastructure including (tunnels with length equal or exceeding 400m with a reinforced concrete covered section of 60m long x 16m wide x 8.5m high, stormwater drainage, pumping station, sewerage, potable water networks and electrical networks and street lighting, in addition to roads, hardscaping and street furniture, and landscaping). Works shall also  rehabilitation and widening of some stretches, and upgrade of a number of existing streets in the heart of the City of Beirut. The considered streets constitute major ways for the in-town circulation of vehicles and pedestrian traffic in addition to being considered the center for major services, touristic and economic activities including general trading and commerce.

 

 

Location

The Works covered by the current Contract include undertaking Works in the following streets:

 

AustraliaBachir

Kassar

Berlin

Borj Abi Haydar

Jabal arab

Khalil Moutrane

Republic

Saeb Salam

BlvSaeb Salam

BlvUnitee

Venzuella

Verdun

 

Scope of Work

The extent of works includes without limitation, the following main elements:

 

Engineering and Permits

Identification of utilities

Geotechnical Investigations

Material Testing

Coordination with the Client and various authorities

Traffic management plans during construction

Schedule, planning and progress program

Shop drawings

AsBuilt Drawings

Earthworks

Earthworks and trenching works

Structural Works: (as required by Contract Documents) including tunnels, retaining walls, parapets, culverts, concrete barriers, and others

Pavement works

Milling

Subbase

Base course

Prime coat

Asphalt binder course

Tack coat

 Asphalt wearing course

Reinstatement of trenches

Traffic markings and signs

Installation/replacement of utility networks

Telephone (including civil works for public payphone)

Electrical (including MV and/or LV cables)

Potable Water Networks

Sewer Networks

Storm water drainage Networks

Traffic signs and signals

Relocation of existing utility networks

Telephone Cables

Electrical Cables

Potable Water Networks

Sewer Networks

Storm water drainage Networks

Traffic signs and signals

Streets Upgrading

Construction of new sidewalks, kerbs, and rehabilitation (realignment and relevelling)  of existing tiling, sidewalks and kerbs

New street lighting and complete rehabilitation of existing street lighting poles

Street furniture and replacing and /or removal of existing furniture as required

Safety barriers, handrails (monorails) on concrete parapets

Landscaping